Lot Clearing in Placerville
Planning lot clearing in Placerville before you build? Call (530) 499-4858. We ask about the lot, find a local clearing professional, arrange a visit on the ground, and help you set the quotes side by side. A lot is usually under a few acres, so the job is smaller than a big parcel. It still has steps that need to happen in the right order.
Home › Lot clearing
What gets cleared first on a building lot
If you are clearing land to build a house, start with the footprint. The first things to go are whatever sits where the house, the driveway and the septic area will be. Everything else waits until you know what the plans and the county will allow.
Many owners clear too much too early. Trees you keep give shade and a screen from the road. Trees you cut cannot be put back. Mark the ones that stay with tape before a machine shows up.
The usual order of work
Most lots follow the same path. Your own lot may skip a step or add one.
- Walk the lot with the plans and mark what stays, especially oaks.
- Ask the county about permits, and ask CAL FIRE about timberland.
- Cut the trees that are in the way, and cut up the wood.
- Clear the brush and small growth.
- Deal with the stumps: grind them or pull them.
- Grade the pad and the drive, if the plans call for it.
- Spread or move the chips and wood left over.
The order matters because the later steps depend on the early ones. Stumps cannot be ground until the tree is down. Grading cannot start until the stumps are out of the way.
What lot clearing costs in the guides
Guides price a lot by its size and by how thickly it is wooded. The ranges below are national, and none of them is a Placerville quote.
| Lot size | Lightly forested | Densely forested |
|---|---|---|
| Half an acre (Angi) | $250 to $1,000 | $1,800 to $2,800 |
| One acre (Angi) | $500 to $2,000 | $3,600 to $5,600 |
| One acre (Bob Vila) | $500 to $2,000 | $3,000 to $5,600 |
Angi clear-land guide, dated September 28, 2026. Bob Vila, dated February 28, 2023.
Fixr, in a guide dated January 31, 2025, says wooded lot clearing costs $500 to $5,000 per acre depending on density. Angi lists $100 to $150 per stump when stumps are pulled during clearing, and Bob Vila says around $345 per stump. A lot with many stumps adds up fast. Angi also notes that renting a forestry mulcher runs $1,200 to $3,000 per day, plus insurance and transport.
Get the price in writing, then check what it leaves out, such as stumps, hauling and grading. Bigger parcels are priced by the acre on the land clearing services page.
Permits and rules for a building lot
Here is what the public sources say, and who to ask. None of it is legal advice.
Grading
El Dorado County requires a grading permit for earth moving on private property in the unincorporated county. The county lists some small jobs as exempt, and its page says an exemption does not apply where a cut or fill could endanger a structure. Ask Planning and Building whether your job is one of the small ones. If your lot is in the city limits of Placerville, the city handles it. Ask the county or the city before the plans are final, not after.
Timberland and a new house
CAL FIRE's handout says cutting trees on timberland and then using the ground for a house or a driveway counts as timber operations. It adds that this holds even with an approved building permit. A foothill lot may or may not be timberland. Ask CAL FIRE before you cut.
Oaks
The county oak ordinance covers private land in the unincorporated area. Read the county oak page and ask the planning office how it applies to the oaks on your lot.
If an oak stays, think about its roots. UC says reduced summer water matters especially for native California oaks, which grew up without summer water. A new lawn with a sprinkler under an old oak works against that.
Digging for utilities
Under state law, excavation includes grading, trenching and digging. Before digging starts, the law sets a wait of at least two working days after the 811 notice, and the call is free. USA North 811 tells owners who hire someone to dig to make sure the contractor follows that process. Ask each professional whether the 811 call will be made, and ask the utility crew too.
Nesting birds
California Fish and Wildlife says nesting season for many bird species runs February through August. The season can vary by place, and some birds nest year-round. Removing vegetation can destroy active nests. Clearing outside February through August lowers the odds, but check for active nests first, or ask about a nest survey by a consulting biologist when work cannot wait.
Wet ground and the calendar
Winter rain is heavy here. The NOAA station named PLACERVILLE 0.9 NE shows normals of 6.64 inches in January and 7.01 inches in February. Bare ground gets the full force of that.
Waiting for drier months pushes the work toward fire season, when the county bans burning. Ask the professional how the schedule fits both.
Use the chips on your own lot
Chips from the clearing do not have to leave. UC publication 8504 recommends 3 to 4 inches of wood chip mulch around landscape plants, kept at least 1 foot from tree trunks. Keep chips away from the house, though. The draft Zone 0 rule lists mulch and wood chips among the fuels barred from the strip within 5 feet of a building. The rule is still being finalized by the Board of Forestry. Ask your fire district what it expects.
Defensible space once the house is up
On state responsibility land, the state wants 100 feet of defensible space around a house. Plan the lot with that distance in mind. Where trees stand close to the house, ask CAL FIRE or your fire district what to thin, and what to leave.
Access, boundaries and the neighbors
Tell every professional how a truck and a machine will reach the lot. Mention a narrow drive, a gate, a ditch or a power line overhead. Walk the lot lines too, so the machine stops where your land stops.
The county's Good Neighbor policy runs both ways. If a fire hazard on one parcel threatens a structure within 100 feet of the line, the owner of that parcel must remove it on their side. A bare lot next to a wooded one is a good reason to talk with the neighbor before the work starts.
Picking the right kind of job
A small lot of brush and young trees may need only mulching. See forestry mulching in Placerville for what that means. A lot of big trees and stumps needs the longer job, covered on the land clearing services page. For grown-over ground beside a building, the brush clearing page fits better.
Land farther out has its own pages. See forestry mulching in Pollock Pines and forestry mulching near Somerset. When the plan is ready, use the quote form.
Before you sign
Look the contractor up on the license board's Check a License page. Jobs valued at $1,000 or more, or any job that needs a building permit, call for a license. Jobs over $500 need a written contract. Its lookup lists any license a contractor holds.
Quick answers
How much does it cost to clear off a lot?
In national guides, a half acre runs $250 to $1,000 if lightly forested and $1,800 to $2,800 if dense. An acre runs $500 to $2,000 or $3,600 to $5,600. A written quote from someone who has seen the lot is the only real number.
How do I start clearing land to build a house?
Mark the footprint, the drive and the septic area first. Keep the trees you want and tape them. Then ask the county about permits and CAL FIRE about timberland before anything is cut.
What is the best way to clear land of small trees?
Small trees and brush can be chewed up in place by a mulcher. Larger trees are cut and the wood is moved. Stumps are ground or pulled either way. The best method depends on what the lot will be used for.
Can I clear my land without a permit?
We cannot say for your lot. Grading, oaks and timberland have separate rules. Ask El Dorado County Planning and Building and ask CAL FIRE.
How many acres can a mulcher clear in a day?
That depends on how thick the growth is and how steep the ground runs. Ask each professional how long your lot will take.
Should I clear the whole lot before I build?
Usually not. Clear the footprint and the access first. Keep trees you want, and mark them. Once a house stands, the state wants defensible space of 100 feet around it on state responsibility land, so ask your fire district what that means on your lot.